Hull Marking-Painting of Markings on Hull and Bulwark, Ships name on port and stbd bow, Name and port of registry on stern, Draft marks on port and stbd bow, midship and stern, Freeboard/plimsol mark on port and stbd midship, Bulbous bow marks on port and stbd bow, Thruster marks on port and stbd bow
Port & Stbd Anchors and chains to be ranged out in drydock, cleaned, inspected, calibrated and marked with band its strap
Kort nozzle pressure test @ 5 bar, HP 3,000psi washing, hard scrapped, grit blasting SA 1.5 and painting
To remove cement and bottom plugs, Rudder HP 3,000psi washing, hard scrapped, grit blasting SA 1.5 and painting, Stern Roller HP 3,000psi washing, hard scrapped, grit blasting SA 1.5 and painting
Rudder-Remove ruder to dock bottom for inspection, Renew rudder stock lip seal spares, Dismantling of Rudder stock from steering gear & overhauling
Rope guard HP 3,000psi washing, hard scrapped, grit blasting SA 1.5 and painting
Zinc anodes to remove and re-install with new zinc anodes
Sea chest: hand scrap of barnacles, HP Water Jet Cleaning, Gritblast to SA1
Remove sea chest grating, clean by HP Washing, blasting, painting, fit the gratings back into place and replace the seizing wires with new stainless steel wire
Thruster grid to be removed / cleaned / sandblasted SA-1.0 and painting
Dismantling of sea water strainers
Sea valves to dismantle & overhaul, clean, free up, lap in for DNV GL Class inspection
Replacement of corroded top plate of the BW tank; Helideck railing blasting/painting & reinstallation
Tanks Hydro & Air Pressure test
Replacement of steel plate as per UTM report Shelter deck, WBT #5, Shell plating PS, Helicopter deck
Main mast repair
Helideck & Bridge drain lines repair
UT test & repair of the Cracked weld seam on shell plates
Modification of Bracket for new VSAT antenna
Chemical cleaning / water flushing of horizontal & Vertical fender
Repair on V-SAT mast, Fabrication & Installation new pole for pull out mast
Fabrication & Installation of new Benches for Gyrocompasses
VESSEL PORTHOLES CORRODED FRAMES REPAIR
REMOVING, FABRICATION AND INSTALLATION OF THE CORREDED/DEFECTED VENT. HEADS
REPAIR OF THE DAMAGED FRC BOAT SHELL PLATES
scope of Work
REPAIR / REPLACEMENT OF THE BWT No:5 DEFECTED DISCHARGE LINE
SCRAPPING / HP WASHING / BLASTING / PAINTING OF THE AZIMUTH THRUSTER AMD AZIMUTH THRUSTER SEA CHEST BOX
HP WASHING / BLASTING / PAINTING OF THE UNDER HELIDECK PS & STBS CONSOLES
Fabrication / Machining of the 8 sets of bronze inserts for Streamer Winch clamps
REPAIR OF STRAINER
Replace pipelines to FW tank
Replace fire pipeline on superstructure deck
Repair shape's pole on monkey islend
CORRECTION OF PLIMSOL MARKS ON PS & STBS SHELL PLATES AFLOAT
SEISMIC PARTS UNLOADING/LOADING/STORAGE AND TARNSPORTATION
Pressure test of seismic HP air system
Chemical cleaning/flushing of HP air system an bottles
Barovane system fabrication & installation as per provided drawing
Hot Oil Flushing(NAS 6) and Testing of Barovane new installed tubing & pipeline
Test pressure 375bar
Installation lubrication pump and piping
Hot oil flushing (NAS 6) and Testing of Lubricating oil pump tubings
Test pressure 600bar
Remove the ODIM Monowing hydraulic system on port/stbd gun deck