Reinforcement of AGR Deck for installation of IKM Equipmemt
Installation Starting air system
Drain pipe installation
Painting of side shells 4 side
Painting of AFT Life boat
Painting of Moon pool
Painting of FWD Passage way
Painting of STBD&PS Burner boom platform
Painting Top of helideck
Fabrication and installation of mud agitation system pipes and supports
Hyrotesting of new line
Painting of pipies, supports and burn marks occurred by this job, scaffolding, lifting activities and tank ventilation for entrance and working purpose
Shutt of damper installation, actuator and controller upgrading
New ducting installation for chiller unit to drill cabin
Painting Columns Scrapping
HP Washing and Cosmetic Spray Painting (Below water line & RED part)
Fabrication of 4 life boat cradles, lifting of 4 life boats and 1 FRC from sea to designated area