NT Flagman

Assembly, upgrade, integration, machinery, coating and survey works for the lift boat NT Flagman.

Project Info

Vessel information

Vessel Name
NT Flagman
Vessel Type
Lift Boat
IMO
9752113
Client
Nurly Tolkun Turkmenistan
Duration
13.12.2021 - 04.07.2022
Service
Repairs and Conversions

Technical parameters

Principal Dimensions

Principal Dimensions

Length
40.06 m
Breadth
23.77 m
DWT
1040 t

Asset

Lift

Lift boat

Length

40.06m

Principal dimension

DWT

1040t

Deadweight

Client

Nurly Tolkun

Turkmenistan

Overview

Project execution

The NT Flagman project covered docking, transfer to repair slab, assembly of legs, wings, pads, crane systems, thrusters, gensets, hydraulic lines, piping and electrical systems. The scope also included ventilation upgrades, machinery repairs, blasting and painting, fire and PA/GA systems, CO2 system installation and light ship survey for Nurly Tolkun Turkmenistan.

Scope of Work

Repair scope

  • Unloading the wings, legs, main crane accessories and other accessories from vessel
  • Docking vessel and transferring the vessel to repair slab for assembly
  • Assembly of the wings, lower and upper part of legs and pads
  • Assembly and modification of electrical cables, pipe systems and hydraulic lines
  • Installation and assembly of the main crane and preparation of engine room
  • Upgrading existing machinery space ventilation for larger generators and installing new ventilation for two new thruster compartments
  • Degreasing, cleaning and painting of leg ends with yellow paint
  • Assembly of thrusters, gensets and emergency genset
  • Fabrication and installation of handrails and vertical ladder for aft thruster gondola integration
  • Installation of new electrical switchboards, panels, cables and equipment
  • Repair of ME cylinder block damaged area with Belzona
  • Blasting and painting underwater area and topside, including draft mark painting
  • Machining of shafts, installation of shafts and propellers
  • Installation of new exhaust piping for the new generators
  • Installation of exhaust pipe insulation for new gensets
  • Blasting and painting of fresh water tanks
  • Fabrication and installation of keel cooler protection
  • Installation of fire alarm system and PA/GA system
  • CO2 system installation
  • Flush hatch fabrication and installation
  • Vessel light ship survey

Timeline

Milestone control

Each stage is organized around production readiness, quality records, and yard coordination.

1

Stage 01

Docking and unloading

The vessel was docked, transferred to the repair slab and prepared for unloading, assembly and integration works.

2

Stage 02

Assembly and integration

Legs, wings, pads, crane equipment, thrusters, gensets, piping, hydraulic and electrical systems were assembled and upgraded.

3

Stage 03

Coating and survey

Blasting, painting, fire and safety systems, CO2 installation and light ship survey supported final project close-out.

Video

NT Flagman lift boat repair and conversion works

Service portfolio

Explore more Repairs and Conversions