Muslim Magomayev

Hull cleaning, coating, fender works and Ampelmann gangway installation support for the offshore supply ship Muslim Magomayev.

Project Info

Vessel information

Vessel Name
Muslim Magomayev
Vessel Type
Offshore Supply Ship
IMO
9732292
Client
Caspian Marine Services LTD
Duration
08.07.2015 - 29.07.2015
Service
Repairs and Conversions

Technical parameters

Principal Dimensions

Principal Dimensions

Length
70m
Breadth
16.5m
DWT
112t

Asset

OSV

Offshore supply ship

Length

70m

Principal dimension

DWT

112t

Deadweight

Client

CMS

Caspian Marine Services

Overview

Project execution

The Muslim Magomayev repair scope included underwater hull scraping and cleaning, external hull coating above and below the waterline, steel plate renewal, hull marking works, tire fender removal and reinstallation, main mast ladder fabrication, Ampelmann pedestal handling and gangway installation, sea chest air vent adaptor fabrication and sewage drain line repair.

Scope of Work

Repair scope

  • Scraping of barnacles and marine growth from external underwater hull
  • Underwater cleaning by high pressure water washing
  • Painting of external hull underwater and above water hull
  • Renewal of hull plate
  • Painting of draft marks at four locations and Plimsoll marks
  • Painting of Piano Keyboard Design on hull port and starboard
  • Painting of company web page WWW.CASPMARINE.COM on hull port and starboard
  • Removal and reinstallation of 16 rubber tire fenders
  • Aluminum ladder step fabrication for main mast
  • Offloading of owner's Ampelmann pedestal from truck, transport to floating unit and lifting into vessel
  • Installation of owner's Ampelmann gangway on the vessel
  • Fabricated and machined adaptor for sea chest air vent system
  • Repair of sewage drain line

Timeline

Milestone control

Each stage is organized around production readiness, quality records, and yard coordination.

1

Stage 01

Hull treatment

The underwater hull was cleaned, scraped and painted, with hull plates and markings renewed.

2

Stage 02

Deck and fender works

Rubber tire fenders, mast ladder steps and hull visual identity works were completed.

3

Stage 03

Ampelmann and systems

Ampelmann pedestal and gangway handling, sea chest vent adaptor fabrication and sewage drain line repair were completed.