Lashin 2

Mooring equipment upgrade works for the Lashin 2 barge, including bollards and Panama chocks.

Project Info

Vessel information

Vessel Name
Lashin 2
Vessel Type
Barge
IMO
060073
Client
Blue Water Shipping Kazakhstan LLP
Duration
25.07.2018 - 04.09.2018
Service
Repairs and Conversions

Technical parameters

Principal Dimensions

Principal Dimensions

Length
91.2m
Breadth
16m

Asset

Barge

Deck barge

Length

91.2m

Principal dimension

Scope

Mooring

Bollards and chocks

Client

Blue Water

Kazakhstan LLP

Overview

Project execution

The Lashin 2 project focused on upgrading the barge mooring arrangement. Baku Shipyard carried out bollard replacement and upgrade works, removal and installation of Panama chocks, and fabrication of Panama boxes to support the required mooring capacity.

Scope of Work

Repair scope

  • Upgrade of 20 double bollards to NS2584 DN500 type with SWL 510 kN
  • Dismantling of 12 bollards above deck
  • Upgrade of 12 Panama chocks to support suitable mooring for a minimum of 625 kN
  • Removal of 8 Panama chocks
  • Installation of 8 Panama chocks
  • Fabrication of 8 Panama boxes
Lashin 2 barge at Baku Shipyard

Timeline

Milestone control

Each stage is organized around production readiness, quality records, and yard coordination.

1

Stage 01

Mooring survey and preparation

The existing deck mooring arrangement was prepared for bollard and Panama chock modification works.

2

Stage 02

Bollard and chock works

Bollards were dismantled and upgraded, while Panama chocks and boxes were removed, fabricated and installed.

3

Stage 03

Completion

The upgraded mooring arrangement was completed to support the specified load requirements.