Islay
Hull treatment, coating, rudder, shaft, sea chest, piping and electrical repair works for the tug and supply vessel Islay.
Project Info
Vessel information
- Vessel Name
- Islay
- Vessel Type
- Tug / Supply Vessel
- IMO
- 9246073
- Client
- Caspian Marine Services LTD
- Duration
- 06.08.2014 - 30.01.2015
- Service
- Repairs and Conversions
Technical parameters
Principal Dimensions
Principal Dimensions
- Length
- 77.5m
- Breadth
- 16.3m
- DWT
- 2665t
Overview
Project execution
The Islay project included underwater hull cleaning, high-pressure washing, blasting and coating, markings renewal, sea chest works, rudder and shaft repair, propeller-area works, fabrication of shaft protectors and pad eyes, bridge coating, piping repairs and electrical system checks.
Scope of Work
Repair scope
- Cleaning of underwater areas by scrapers
- High-pressure washing of underwater hull areas up to 3500 psi
- Blasting and painting of underwater and waterline areas
- Topside painting above waterline
- Black water collecting tank renewal
- Renewal and highlighting of freeboard, draft marks, ship name, IMO marking and port of registry
- Removal of tangled synthetic rope from the propeller area
- Sea chest grating opening, cleaning, blasting and painting
- Protection of anodes, propeller blades, bow thruster blades, echo sounder, speed log and side scuttles before blasting and painting
- Cleaning and two-coat painting of bridge areas PS and STBD
- Mounting of fenders with new chains, shackles and drilled chain holes
- Conservation of PS rudder stock and stock nut
- Fabrication of blind plug for PS shaft
- Transport of shaft and propeller shaft to mechanical workshop for repair
- Fabrication and installation of pad eyes in engine room
- Fabrication of new shaft protector
- Rudder shaft dismantling support, inspection openings and reinstatement
- Foundation stand seating fabrication for shaft
- Shaft inspection and repair on lathe machine
- MPI testing of shaft and stock
- Shaft transportation, crane lifting and installation onboard
- Cutting and installation of rudder opening for PS rudder dismantling
Timeline
Milestone control
Each stage is organized around production readiness, quality records, and yard coordination.
- 1
Stage 01
Hull preparation and coating
Underwater hull areas, waterline, topside, sea chest and markings were cleaned, blasted, protected and coated.
- 2
Stage 02
Rudder and shaft works
Rudder stock, shaft, shaft protector, pad eyes and related workshop repairs were completed with MPI testing.
- 3
Stage 03
Systems and reinstatement
Piping, fendering, bridge coating and associated electrical and mechanical reinstatement works were completed.