Castoro 12

Cutting, separation, drydocking and transfer preparation works for the Castoro 12 pipe lay barge.

Project Info

Vessel information

Vessel Name
MV Castoro 12
Vessel Type
Pipe Layer
IMO
9333307
Client
North Caspian Service Company LLP / Saipem Portugal Comercio Maritimo, Sociedade Unipessoal LDA
Duration
02.02.2020 - 11.04.2020
Service
Repairs and Conversions

Technical parameters

Principal Dimensions

Principal Dimensions

Length
101m
Breadth
29.35m
DWT
1200t

Asset

Pipe layer

Barge

Length

101m

Principal dimension

DWT

1200t

Deadweight

Client

Saipem

NCSC / Saipem

Overview

Project execution

The Castoro 12 pipe lay barge required a dedicated conversion and preparation scope to allow transfer out of the Caspian Sea through the Volga-Don channel. Baku Shipyard carried out drydocking, slab transfer, structural preparation, cutting along the centreline, disconnection of cross systems, temporary closures, protection works and final coating touch-up for safe onward transportation.

Scope of Work

Repair scope

  • Preparation works, including removal of unnecessary structures and warehouse parts
  • Drydocking and undocking of the barge
  • Transfer of the barge to the repair slab
  • Steel works for installation of temporary supports for the helideck and beveling area
  • Cutting along centreline and temporary closure of openings
  • Disconnection of cross piping and cabling
  • Installation of fenders on each pontoon at centreline
  • Dismounting of helideck planks and cutting of helideck beams
  • Dismounting of the main mast
  • Dismounting of main crane A-frame and stinger
  • Installation of towing bridles and emergency bridles on each pontoon
  • Protection of cables, lighting and special equipment from hot works with fire blankets and metal shields
  • Power tooling of burned areas on the cut line where necessary and touch-up painting with primer coat

Timeline

Milestone control

Each stage is organized around production readiness, quality records, and yard coordination.

1

Stage 01

Preparation and docking

The barge was prepared for transfer works, drydocked and moved to the repair slab for controlled structural operations.

2

Stage 02

Separation works

Centreline cutting, system disconnections, helideck, mast, crane A-frame and stinger dismantling were completed.

3

Stage 03

Transport readiness

Fenders, towing bridles, emergency bridles, temporary closures, hot-work protection and coating touch-ups were completed for onward transfer.

Video

Castoro 12 pipe layer works at Baku Shipyard