Castoro 12
Cutting, separation, drydocking and transfer preparation works for the Castoro 12 pipe lay barge.
Project Info
Vessel information
- Vessel Name
- MV Castoro 12
- Vessel Type
- Pipe Layer
- IMO
- 9333307
- Client
- North Caspian Service Company LLP / Saipem Portugal Comercio Maritimo, Sociedade Unipessoal LDA
- Duration
- 02.02.2020 - 11.04.2020
- Service
- Repairs and Conversions
Technical parameters
Principal Dimensions
Principal Dimensions
- Length
- 101m
- Breadth
- 29.35m
- DWT
- 1200t
Overview
Project execution
The Castoro 12 pipe lay barge required a dedicated conversion and preparation scope to allow transfer out of the Caspian Sea through the Volga-Don channel. Baku Shipyard carried out drydocking, slab transfer, structural preparation, cutting along the centreline, disconnection of cross systems, temporary closures, protection works and final coating touch-up for safe onward transportation.
Scope of Work
Repair scope
- Preparation works, including removal of unnecessary structures and warehouse parts
- Drydocking and undocking of the barge
- Transfer of the barge to the repair slab
- Steel works for installation of temporary supports for the helideck and beveling area
- Cutting along centreline and temporary closure of openings
- Disconnection of cross piping and cabling
- Installation of fenders on each pontoon at centreline
- Dismounting of helideck planks and cutting of helideck beams
- Dismounting of the main mast
- Dismounting of main crane A-frame and stinger
- Installation of towing bridles and emergency bridles on each pontoon
- Protection of cables, lighting and special equipment from hot works with fire blankets and metal shields
- Power tooling of burned areas on the cut line where necessary and touch-up painting with primer coat
Timeline
Milestone control
Each stage is organized around production readiness, quality records, and yard coordination.
- 1
Stage 01
Preparation and docking
The barge was prepared for transfer works, drydocked and moved to the repair slab for controlled structural operations.
- 2
Stage 02
Separation works
Centreline cutting, system disconnections, helideck, mast, crane A-frame and stinger dismantling were completed.
- 3
Stage 03
Transport readiness
Fenders, towing bridles, emergency bridles, temporary closures, hot-work protection and coating touch-ups were completed for onward transfer.