Dry-docking/undocking of the vessel inclusive arrangement of the tug boats
HP washing of the main hull underwater areas on vessel arrival
Transferring of the vessel to repair slab
Cutting and removing of the transporting grillages, sea-fastening, temporary handrails, bumpers, blanking plates, unloading of the cut off units
Alignment of the deformation on cutting lines
Welding of the cut units to the main hull
Re-installation of Draft marks and permanent hull markings after assembly
NDT testing of the welds as per Class requirement
Tank tightness test of the reassembled tanks (air test)
Steel works for relocation of 6 (six) 2x25 t bollards
Re-installation of the life boats, davits and motors
Assembling of hydraulic system
Electrical works for installation of Life boats, davits and motors supplier Technical documentation, Technical Data
Assistance on Life boat davit electrical test and test of hydraulic system
Installation of dismantled equipment (switches, electrical cables) on reassembled wing tanks area
Installation of ballast system pipes and alignment of seachest fixed pipes on reassembled wing tanks area
Power tooling, blasting where necessary, touch up painting of the reassembled wing tanks as per paint specification and cosmetic coating of external hull, with Yard supplied paint material